- varnish trim
I *think* but am not sure, that we've now got everything we need final coated.
- install wood floors on upper level and... (all done except for some little strips that need to be ripped for the edges)
- ...down stairs to main level
- install trim on
- hang laundry room pocket door (maybe not necessary before move-in)
- caulk the bathtub
- build bathroom shelves
- install bathroom mirror (which, as Matt's pointing out, is more like design/buy/build/install bathroom mirror)
- install closet rod
- build doors for the low closet (Maybe. We may just hang fabric on a tension rod.)
- ...finish opening between old and new
- install laundry sink (nearly done, but there is a minor leak and I'm not sure if its resolved, so won't cross it off until I'm certain)
- install handrail (Reu and Rin helped me purchase these, and we've got the first coat of varnish on)
And I have photos to share, but won't get them up until tomorrow most likely.
Even more significant, we have a moving date!!! In just over two weeks a small moving crew will show up at Matt's mom's and bring her things over here. Hiring movers accomplishes two things: first, it means the date is solid and won't tend to float, and secondly, it means that Matt doesn't have to wrestle her piano up the stairs!!
| "Dew" thinks he's sanding with Dad |
| Owen nails on window trim in the laundry room |
| Window trim at the stairs, tying into the trim band that separates the two wall colors in the stair well and runs at the top of the larger shelf. |
| Wood floors complete in the front room (with the exception of a tiny strip by the wall that needs to be ripped to size.) |
| The hallway at the top of the stairs is finished up to the nosing of the first stair. Stairs will be a whole new learning curve. ;) |
| Look! Stacked washer and dryer! (And the blue iPad in the doorway so we can monitor Reuben. He's always in the pictures one way or another, it seems!) |